| August 10, 2010
2010-01-052-007
ADAMS COUNTY, ILLINOIS
WIND ENERGY CONVERSION SYSTEMS REGULATIONS
An Ordinance to repeal and replace the Adams County, Illinois
Wind Energy Conversion System Regulations
adopted by the Adams County Board on January 12 th,
2010
2 August
10, 2010
ADAMS COUNTY, ILLINOIS
WIND ENERGY CONVERSION SYSTEMS REGULATIONS
I. INTRODUCTION
II. DEFINITIONS
III. APPLICABILITY
IV. PROHIBITION
V. PROCEDURE
VI. SITING APPROVAL APPLICATION
VII. DESIGN AND INSTALLATION
VIII. OPERATION
IX. PUBLIC PARTICIPATION
X. LIABILITY INSURANCE
XI. DECOMMISSIONING PLAN
XII. REMEDIES
XIII. PERMIT TRANSFER
XIV. FEE SCHEDULE AND PERMIT REVOCATION
XV. INDEMNIFICATION, REIMBURSEMENT AND HOLD HARMLESS AGREEMENT
XVI. VARIANCE AND MODIFICATION
XVII. INTERPRETATION
XVIII. SEVERABILITY
XIX. REPEAL
XX. CERTIORARI PROCEDURE
XXI. EFFECTIVE DATE
3 August 10, 2010
I. INTRODUCTION
A. Title
This Ordinance shall be known, cited and referred to as the Adams
County Wind Energy Siting Ordinance.
B. Purpose
This Ordinance is adopted for the following purposes:
1. To assure that any development and production of wind-generated
electricity in Adams County is safe and effective;
2. To facilitate economic opportunities for local residents;
II. DEFINITIONS
A. "Applicant" means the entity or person who submits to the County,
pursuant to Section V of this Ordinance, an application for the siting
of any WECS or Substation.
B. "Fall Zone" means the area, defined as the farthest distance from
the WECS Tower base, in which a WECS Tower will collapse in the event of
a structural failure. This area is the total height of the structure
plus length of blade.
C. "Feeder Line" means any power line that carries electrical power
from one or more wind turbines or individual transformers associated
with individual wind turbines to the point of interconnection with the
electric power grid.
D. "Financial Assurance" means reasonable assurance from a credit
worthy party, examples of which include a surety bond, trust instrument,
cash escrow, or irrevocable letter of credit.
E. "Meteorological Tower" means those towers which are erected
primarily to measure wind speed and direction plus other data relevant
to siting a WECS Project. For purposes of this ordinance, Meteorological
Towers do not include towers and equipment used by airports, the
Illinois Department of Transportation, or other similar applications or
government agencies, to monitor weather conditions.
F. "County Board" means the Adams County Board.
G. "Operator" means the entity responsible for the day-to-day
operation and maintenance of the WECS, including any third party
subcontractors.
H. "Owner" means the entity or entities with an equity interest in
the WECS(s), including their respective successors and assigns. Owner
does not mean (i) the property owner from whom land is leased for
locating the WECS (unless the
4 August 10, 2010
property owner has an equity interest in the WECS); or (ii) any
person holding a security interest in the WECS(s) solely to secure an
extension of credit, or a person foreclosing on such security interest
provided that after foreclosure, such person seeks to sell the WECS(s)
at the earliest practicable date.
I. "Primary Structure" means, for each property, the structure that
one or more persons occupy the majority of time on that property for
either business or personal reasons. Primary structure will be on a
permanent foundation, served with electricity, potable water, and sewer
or septic system. Primary Structure includes structures such as
residences, commercial buildings, schools, churches, hospitals, retail
buildings and day care facilities. Primary Structure excludes ancillary
structures which are not used for residential purposes such as hunting
sheds, storage sheds, pool houses, unattached garages and barns.
J. "Property Line" means the boundary line of the area over which the
entity applying for a WECS permit has legal control for the purposes of
installation of a WECS. This control may be attained through fee title
ownership, lease, easement, or other appropriate contractual
relationship between the project developer or Owner and landowner.
K. "Public Conservation Lands" means land owned in fee title by state
or federal agencies and managed specifically for conservation purposes,
including but not limited to state and federal parks, state and federal
wildlife management areas, state scientific and natural areas, and
federal wildlife refuges and waterfowl protection areas. Public
conservation lands do not include private lands upon which conservation
easements have been sold to government agencies or non-profit
conservation organizations. Public conservation lands also do not
include private lands for which the owners have entered into contractual
relationships with government or non-profit conservation organizations
for conservation purposes.
L. "Structural Engineer" means a qualified individual who is licensed
as a structural engineer in the State of Illinois.
M. "Substation" means the apparatus that connects the electrical
collection system of the WECS(s) and increases the voltage for
connection with the utility's transmission lines.
N. "Transmission Line" means those electrical power lines that carry
voltages of at least 69,000 volts (69 KV) and are primarily used to
carry electrical energy over medium to long distances rather than
directly interconnecting and supplying electric energy to retail
customers.
O. "Wind Energy Conversion System" ("WECS") means all necessary
devices that together convert wind energy into electricity, including
the rotor, nacelle, generator, WECS Tower, electrical components, WECS
foundation, transformer, and electrical cabling from the WECS Tower to
the Substation(s).
5 August 10, 2010
P. "WECS Project" means the collection of WECSs and Substations as
specified in the siting approval application pursuant to Section V of
this Ordinance.
Q. "WECS Tower" means the support structure to which the nacelle and
rotor are attached.
R. "WECS Tower Height" means the distance from the rotor blade at its
highest point to the top surface of the WECS foundation.
S. "Wind Turbine" means any piece of electrical generating equipment
that converts the kinetic energy of moving wind into electrical energy
through the use of airfoils or similar devices to capture the wind.
III. APPLICABILITY
A. This Ordinance governs the siting of WECSs and Substations that
generate electricity to be sold to wholesale or retail markets.
B. Owners of WECSs with an aggregate generating capacity of 0.5MW or
less who locate the WECS(s) on their own property for on site use are
not subject to this Ordinance.
IV. PROHIBITION
No WECS or Substation governed by Section III A. of this Ordinance
shall be constructed, erected, installed, or located within the County,
unless prior siting approval has been obtained for each individual WECS
and Substation pursuant to this Ordinance.
V. PROCEDURE
A. Filing of an Application
The Applicant for a WECS approval shall file twenty-five (25) copies
of application, including ten (10) full-size copies of exhibits and
fifteen (15) reduced copies of all exhibits, with the County Clerk,
together with the appropriate site review application fee. The Applicant
is to provide up to ten (10) additional copies of the application to the
County upon request.
B. Fee Schedule
Upon submittal of the application for a WECS, the Applicant shall
submit a non-refundable check to Adams County in the amount of $50,000
which funds will be utilized to review and assess the application.
Should the actual costs to the County exceed $50,000, the Applicant
shall be responsible for those additional costs, including, but not
limited to the costs of outside attorneys, hearing officer, and
consultants (e.g. noise engineers, traffic engineers, and environmental
consultants) and shall remit additional funds to the County within 15
days of
6 August 10, 2010
receipt of a request from the County. The County will submit invoices
in a timely manner. The County will provide itemized records detailing
fund distributions upon request by the Applicant. Such requests may not
occur more than one time per calendar month.
C. County Clerk Responsibilities
The County Clerk upon receiving said application shall do the
following:
1. Accept and date stamp the application as filed. The date stamp of
the County Clerk should be considered the official filing date for all
time limit purposes. Receipt and acceptance of an application by the
County Clerk is pro forma, and does not constitute an acknowledgment
that the Applicant has complied with the County ordinance.
2. The County Clerk shall forward the application to the County
Engineer for a determination of completeness.
3. The County Clerk shall make available a copy of the application
and public record concerning the application for public inspection
during the normal business hours of the County offices. Additionally,
the County Clerk shall provide to any person so requesting, copies of
the application or the public record, upon payment by such persons for
the actual cost of reproduction.
D. Determination of Completeness
After the filing of an application the County Engineer shall make a
preliminary determination of completeness of the application. If, in the
County Engineer’s opinion, the application has addressed the required
elements of an application it will be forwarded to the Transportation,
Building and Technology Committee and the County Board to conduct a
public hearing on the application. If the application is incomplete, the
Applicant will be so notified and the application will not proceed to
hearing unless good cause is shown for the incompleteness.
E. Notice
The Applicant must provide a complete list of all properties adjacent
to a proposed WECS or within one-half mile of a property upon which a
proposed WECS is to be located. The Applicant shall have a notice issued
to every owner of those properties by certified mail, registered mail,
or personal service at the last known address of such owner of property
as identified by the County tax records. Said notice will identify the
nature of the proposed use and the date that a public hearing shall
occur on the proposed use in front of the County Board and that any
person may file an appearance to participate in that hearing and present
witnesses at least five days before the hearing commencement date. Those
notices must be served at least 15 days before the public hearing shall
commence and no earlier than 30 days before the hearing shall commence.
The Applicant shall provide
7 August 10, 2010
evidence of notification or evidence of a "good faith" effort to
contact the property owner prior to the hearing if requested by the
County.
Said hearing notice shall also be published in a circulation of
general publication at least three times before the hearing commences
with the first publication occurring at least 30 days before the hearing
and at least one publication occurring between 7 and 15 days before the
hearing commences.
F. Hearing Officer
The County Board will appoint a hearing officer to preside over the
WECS hearing. The hearing officer shall preside over the public hearing;
establish a record of the proceedings using a certified court reporter,
make decisions concerning the admission of the evidence and the manner
in which the hearing is to be conducted. The County Board may request
that the hearing officer draft a recommendation and proposed findings.
At the commencement of the hearing people wishing to provide sworn
testimony or unsworn public comment will be identified by a sign in
sheet.
G. Entering an Appearance at Hearing and Submitting Exhibits
The hearing officer, any County Transportation, Building and
Technology Committee member and any person who enters an appearance with
the County at least seven days before the hearing will have the
opportunity to question witnesses. Members of the public who do not
enter an appearance at least seven days before the hearing may submit
their questions for witnesses to the hearing officer who at his or her
discretion may ask them of the witness. Any person or persons may appear
at the hearing through an attorney licensed in Illinois. Any person
offering sworn testimony will be subject to questioning. People offering
public comment only (without being sworn in) will not be subjected to
questioning. The hearing officer may limit the time and duration of
questioning and will rule on any objections. At least five copies of any
exhibits which will be used in testimony or questioning must be
furnished by the person offering such exhibit.
If the hearing officer is requested by the Transportation, Building
and Technology Committee to make a recommendation and proposed findings
such shall be provided within three business days of the completion of
the hearing and submitted to the Transportation, Building and Technology
Committee.
H. Committee and Board Action
The Transportation, Building and Technology Committee will consider
the following facts:
1. Whether the application and proposed WECS Project substantially
complies with the WECS ordinance.
8 August 10, 2010
2. Whether the proposed WECS Project is sufficiently protective of
the public health, safety and welfare.
Within 10 days of conclusion of the hearing the Transportation,
Building and Technology Committee shall tender its findings and
recommendations to the County Board. The committee may recommend
approval, approval with request for additional information or
clarification, approval with conditions or denial. Within 30 days of the
conclusion of the public hearing the County Board will meet in public
session and render its decision. The County Board may approve, approve
with conditions, or deny the application.
I. Refiling
Any Applicant, owner or operator whose WECS project application is
denied may not refile a substantially similar application for one year.
If the County Engineer determines an application is substantially
similar to one the Applicant filed within one year it will not be
forwarded to the Transportation, Building and Technology Committee or
the County Board for review.
VI. SITING APPROVAL APPLICATION
A. Form of Applications:
1. All applications shall be in writing on paper of eight and
one-half inches by eleven inches (8 ½" by 11"), eight and one-half
inches by fourteen inches (8 ½" x 14"), or eleven inches by seventeen
inches (11" x 17"). For legibility, full-sized exhibits shall be on
minimum ANSI D size paper.
2. The pages of the application shall be consecutively numbered, and
all exhibits clearly marked and identified.
3. The application including exhibits or graphic presentations shall
also be furnished in an electronic format suitable for reproduction for
public dissemination and for posting on the Adams County Website.
B. The siting approval application shall contain or be accompanied by
the following information:
1. An executed Host Agreement must be appended to, and included as
part of, any WECS application filed with the County. The content of said
Host Agreement will be discussed and negotiated between the Applicant
and the County’s appointed counsel or representatives and will address
issues including, but not limited to, payments in lieu of taxes (Example
attached as Exhibit A), economic issues, renewable energy credit
sharing, carbon credit sharing, reimbursement of County expenses
including consultants, experts and outside attorneys’ fees.
9 August 10, 2010
2. A WECS Project Summary, including: (1) a general description of
the project, including (i) its approximate overall name plate generating
capacity, (ii) the potential equipment manufacturer(s), (iii) type(s) of
WECS(s), (iv) number of WECS(s), and name plate generating capacity of
each WECS, (v) the maximum height of the WECS Tower(s) and maximum
diameter of the WECS(s) rotor(s), and (vi) the general location of the
project; and (2) a description of the Applicant, Owner and Operator,
including their respective business structures.
3. The name(s), address(es), and phone number(s) of the Applicant(s),
Owner and Operator, and all property owner(s), if known, and
documentation demonstrating land ownership or legal control of the
property.
4. A Site Plan for the installation of WECS(s) showing the planned
location of each WECS Tower, substation, anchor bases, and service
roads, Primary Structure(s), Property Lines (including identification of
adjoining properties), all proposed structures, public access roads and
turnout locations, Substation(s), electrical cabling from the WECS
Tower(s) to the Substation(s), ancillary equipment, and third party
transmission lines.
Site Plan information not available at the time of application but to
be obtained prior to construction or through an ALTA survey shall be
provided in a detailed list.
Site Plan information shall be on Illinois State Plane Coordinate
System: NAD 1983 State Plane Illinois West FIPS 1202 Feet. Site plan
information shall also be supplied in an electronic format suitable for
incorporation into the Adams County Geographic Information System
database. Information to be provided should include but not limited to:
tower locations and heights, road easements, substation locations, and
other non-proprietary information.
5. The legal description of each proposed tower and substation
location.
6. All proposed setback dimensions.
7. Topographic site information for the subject property and the
adjacent properties within one-fourth (1/4) mile of the property line of
the subject property indicating contours in ten foot (10’) intervals.
8. Existing structures on properties within one-fourth (1/4) mile of
the property.
9. All existing and proposed underground and aboveground utilities
and identification of all communication towers within two miles of the
proposed WECS.
10 August 10, 2010
10. All rights of way, wetlands, flood plains, drainage ditches,
scenic and natural areas and wooded areas on properties under contract
with the Applicant, and public conservation lands on properties within
1,500 feet of a proposed WECS.
11. Ingress and egress from the site as proposed during construction
and thereafter, which indicates:
a. Proposed road surface and cover.
b. Dust control.
c. Width and length of access route and location of ingress/egress.
d. Road maintenance progress or schedule for proposed use of land.
12. Certified easements, contracts, waivers, and option agreements
for proposed use of the land.
13. Notice by registered mail or certified mail to residential and
commercial microwave communication users within a 2.5 mile radius of the
subject property informing them of the proposed WECS.
14. Utility interconnection details and a copy of written
notification to the utility company requesting the proposed
interconnection.
15. Fire protection plan for the construction and the operation of
the facility.
16. Revegetation plan of the areas that will be disturbed.
17. Description of hours of operation for construction and
maintenance of the facility, numbers of employees and type of traffic
expected to be generated from the site.
18. Public road routes.
19. A permit application filed with the Federal Aviation
Administration;
20. A proposed Decommissioning Plan for the WECS project;
21. All required studies, reports, certifications, and approvals
demonstrating compliance with the provisions of this Ordinance; and
22. Any other information normally required by the County as part of
its permitting requirements for siting buildings or other structures, if
applicable.
C. The Applicant shall notify the County of any changes to the
information provided in Section V.D. above that occurs while the siting
approval application is pending.
11 August 10, 2010
VII. DESIGN AND INSTALLATION
A. Design Safety Certification and Conformance to Codes and Standards
1. WECSs and all components shall conform to all applicable industry
standards, including those of the American National Standards Institute
("ANSI") and the International Electrical Commission. Applicants shall
submit certificates of design compliance that equipment manufacturers
have obtained from Underwriters Laboratories ("UL"), Det Norske Veritas
("DNV"), Germanischer Lloyd Wind Energie ("CGL"), or an equivalent third
party. The WECS shall comply with all applicable local and county codes
for electrical, mechanical and structural components of the facility.
All documents provided for review shall be stamped by a professional
engineer.
2. Following the granting of siting approval under this Ordinance, a
Structural Engineer shall certify, as part of the permit application
that the foundation and tower design of the WECS is within accepted
professional standards, given local soil and climate conditions.
B. Controls and Brakes
All WECS shall be equipped with manual and automatic controls and
mechanical brakes to limit rotation of the blades to a speed below the
design limits of the WECS. A professional engineer or authorized factory
representative must certify that the rotor and overspeed control design
and fabrication conform to good engineering practices. No changes or
alterations from the certified design shall be permitted unless
accompanied by professional engineer or authorized factory
representative’s statement or certification and approved by the company.
C. Electrical Lines
All electrical wires and lines connecting WECS to other WECS or
substation shall be installed underground to the greatest extent
possible.
D. Color, Finish and Appearance
The tower and the blades of the WECS shall be uniform in style and
color and shall be white or gray or another unobtrusive color. The
finish of the tower and the blades shall be matte and nonreflective. The
towers and blades shall be uniform in direction of blade rotation. Any
on site buildings shall be designed such that they are unobtrusive to
minimize the industrial character of the project. All colors, finishes
and design shall conform to all applicable FAA requirements. Except for
required warnings and tower identification, no lettering, company
insignia, advertising or graphics shall be on any part of the tower, hub
or the blades. Standard company insignia may be placed on the nacelle of
the WECS.
12 August 10, 2010
E. Warnings and Tower Identification
Signs warning of the high voltage associated with the WECS shall be
posted at every entrance to the WECS, at the base of all pad mounted
transformers and substations. Visible, reflective, colored objects such
as flags, reflectors or tape shall be placed on the anchor points of
guywires, if any, and along the guywires up to a height of not less than
eight feet (8’) from the ground. A sign that provides emergency contact
information, such as phone number, shall be posted near the tower and
the operations and maintenance building and each tower shall have posted
a unique number for identification purposes.
F. Setback Requirements
1. All WECS Towers shall be set back at least 1.1 times the WECS
Tower Heights from any Primary Structure on a parcel of real property
which is participating in a WECS project by leasing, contracting,
owning, selling, or allowing any portion of said real property to be
used for the placement of a WECS. The distance for the participating
landowner setback shall be measured from the point of the Primary
Structure foundation closest to the WECS Tower to the center of the WECS
Tower foundation. All WECS shall be set back from a Primary Structure on
non-participating lands by at least 1,320 feet. The owner of the Primary
Structure may waive this setback requirement; but in no case shall a
WECS Tower be located closer to a Primary Structure than 1.10 times the
WECS Tower Height or within the Fall Zone of the WECS Tower. All WECS
shall be set back at least 1,500 feet from school property lines unless
waived by the school district.
2. All WECS Towers shall be set back a distance of at least 1.1 times
the WECS Tower Height from public roads, third party transmission lines,
and communication towers. The County may waive this setback requirement.
3. All WECS Towers shall be set back a distance of at least 1.5 times
the WECS Tower Height or the Fall Zone, whichever is greater from
adjacent Property Lines. The affected adjacent property owner may waive
this setback requirement.
4. All WECS Towers shall be set back a distance of at least 1.1 times
WECS Tower Height from the Property Line of any Public Conservation
Lands, and a distance of at least 1500 feet from any river bluff located
on public or private property.
5. The Applicant will need to obtain a variance from the County upon
waiver by either the County or property owner of any of the above
setback requirements. Any waiver of any of the above setback
13 August 10, 2010
requirements shall run with the land and be recorded as part of the
chain of title in the deed of the subject property.
G. Compliance with Additional Regulations
Nothing in this Ordinance is intended to preempt other applicable
state and federal laws and regulations.
H. Use of Public Roads
1. An Applicant, Owner, or Operator proposing to use any County,
municipality, township or village road(s), for the purpose of
transporting WECS or Substation parts and/or equipment for construction,
operation, or maintenance of the WECS(s) or Substation(s), shall:
a. Identify all such public roads; and
b. Obtain applicable weight and size permits from relevant government
agencies prior to construction.
c. Adhere to any temporary postings due to weather conditions
2. To the extent an Applicant, Owner, or Operator must obtain a
weight or size permit from the County, municipality, township or village
to use a public road, the Applicant, Owner, or Operator shall:
a. Enter into a road use and repair agreement with the County and
respective municipalities, township or village.
b. Conduct a pre-construction baseline survey to determine existing
road conditions for assessing potential future damage;
c. Provide a road repair plan to ameliorate any and all damage,
installation or replacement of roads, streets, bridges, intersections,
culverts, storm sewers, or public rights of way
d. The Applicant shall provide a letter of credit or surety bond in
an amount and type approved by the County Engineer and Township Road
District Commissioner to assure compliance with the road repair plan and
road agreement.
I. Drainage Systems
The Applicant shall be responsible for repairing, in a timely
fashion, any damage caused to public drainage systems by the
construction, operation or maintenance of WECS. Financial assurances in
the form of cash or an escrow account, surety bond, or a letter of
credit in a form and amount acceptable to the County Engineer shall be
posted to assure compliance with this section.
14 August 10, 2010
J. Height
The maximum WECS Tower Height shall not exceed 550 feet.
K. Power Lines
All electrical control wiring and power lines less than 69kv shall be
wireless or not aboveground to the extent possible except where wind
farm collector wiring is brought together for connection to the
transmission or distribution network, adjacent to that network.
L. Access Roads
The Applicant shall minimize the number and width of access roads,
minimize cut and fill on sloping terrain and use natural terrain where
feasible for these access points.
M. Blade Clearance
The vertical distance from the grade to the tip of the wind turbine
blade when the blade is at its lowest point must be at least thirty five
feet (35’).
N. Lighting
Tower lighting shall meet all applicable FAA regulations. The
Applicant shall seek leave from the FAA to utilize the least intrusive
lighting possible.
O. Noise Levels
The sound pressure level generated by a WECS shall comply with all
applicable Illinois Pollution Control Board noise regulations.
P. Shadow Flicker
The Applicant shall have an analysis conducted by a qualified
professional of the expected potential shadow flicker. No turbine shall
be located at an area that will result in shadow flicker at a primary
structure on a non-participating landowner property of more than 20
hours per year.
Q. Environmental Impact
The Applicant shall have a third-party qualified professional conduct
analysis to identify and assess any potential impacts on the natural
environment including wetlands and other fragile ecosystems, historical
or cultural sites and antiquities. The Applicant shall take appropriate
measures to minimize, eliminate or mitigate adverse impacts identified
in the analysis. The Applicant shall identify and evaluate the
significance of any effects or concerns that will remain after
mitigation efforts.
15 August 10, 2010
R. Landscaping
Applicant shall minimize the disruption of natural environment,
retain existing vegetation and native plant species to the maximum
extent feasible and replant with native vegetation.
S. Climb Prevention
All WECS shall be designed to prevent unauthorized access to
electrical and mechanical components or access to the towers on the
site. A monopole with an internal ladder and locked access door is
preferred and guy wired towers are disfavored. All towers shall not be
climbable from the ground to fifteen feet (15’) aboveground and all
access doors to towers and equipment shall be lockable.
T. Avian and Wildlife Impact
The Applicant shall have a third party, qualified professional
conduct an analysis to identify and assess any potential impacts on
wildlife and endangered species. The Applicant shall take the
appropriate measures to minimize, eliminate or mitigate adverse impacts
identified in the analysis. The Applicant shall identify and evaluate
the significance of any net effects or concerns that will remain after
mitigation efforts.
U. JULIE Membership
Applicant, after completion of construction, will become a member of
the Joint Utility Locating Information for Excavation ("JULIE"), to
identify the location of any underground electrical lines, to provide a
list of the same to the County, and to register the same with JULIE.
V. Construction Hours
Applicant will undertake all construction activities associated with
the Project only between the hours of 6:00 a.m. and 9:00 p.m. County
Engineer approval must be acquired before making any other change in
work hours due to construction schedule requirements which will not be
unreasonably withheld.
W. Stormwater Prevention
Applicant further agrees to provide a final Stormwater Pollution
Prevention Plan for the Project to Adams County prior to the start of
construction and obtain any other permits required by State and Federal
government agencies.
X. Underground Cable Warnings
All cables, except where installed by trenchless methods, shall have
an underground warning tape buried a minimum 24 inches below grade and a
minimum of 12 inches above cable in the same trench. The warning tape
shall be
16 August 10, 2010
6" wide polyethylene plastic, shall be red in color, and shall have
the appropriate warning stenciled on it.
Y. Agency Permits
Applicant shall obtain all required permits from other governmental
agencies prior to commencing construction or as otherwise required by
the applicable laws and regulations. Copies or evidence of such permits
shall be submitted to the County on or before issuance of the first
Permit for an individual wind tower. Permits shall be obtained from
Adams County for the wind towers.
Z. Substation Noise
Any substation to be constructed and operated as part of the Project
shall utilize commercially available and reasonable sound-attenuation
measures to minimize potential noise impacts for surrounding and nearby
properties, the approval of which shall not be unreasonably withheld by
the County. Substation lighting shall be limited to that necessary to
provide safety and security. Normal substation nighttime operation shall
utilize minimal lighting.
VIII. OPERATION
A. Maintenance
1. The Owner or Operator of the WECS must submit, on an annual basis,
a summary of the operation and maintenance reports to the County. In
addition to the above annual summary, the Owner or Operator must furnish
such operation and maintenance reports as the County reasonably
requests.
2. Any physical modification to the WECS that alters the mechanical
load, mechanical load path, or major electrical components shall require
re-certification under Section VI(A)(l) of this Ordinance. Like-kind
replacements shall not require re-certification. Prior to making any
physical modification (other than a like-kind replacement), the Owner or
Operator shall confer with a relevant third-party certifying entity
identified in Section VI(A)(l) of this Ordinance to determine whether
the physical modification requires re-certification.
3. An Applicant or successor in interest shall have the facility
inspected annually by third party qualified wind power professionals at
their own expense. The third party qualified wind power professional
shall be subject to the approval of the Adams County Engineer. Within 30
days of the inspection a copy of any report must be provided to the
Adams County Engineer. The WECS may not operate unless a certificate is
provided to the Adams County Engineer indicating that the annual
maintenance has been completed and the facility is in good working
17 August 10, 2010
condition. Failure to provide this annual certification may cause the
revocation of the operating permit.
B. Signal Interference
1. WECS shall not be installed in any location where its proximity to
existing fixed broadcast, retransmission or reception antennas for
radio, television or wireless phone or other personal communication
systems would produce electromagnetic interference with signal
transmission or reception unless the Applicant provides a replacement
signal to the affected party that will restore reception to at least the
level present before operation of the wind energy system. WECS shall not
be installed in any location within the line of sight of an existing
microwave communications link where operation of the wind energy system
is likely to produce electromagnetic interference in the link’s
operation unless the interference is insignificant. The Applicant shall
provide the project summary and site plan to all microwave transmission
providers, and all communication tower operators with five miles of any
WECS to address potential conflicts.
2. If, after construction of the WECS, the Owner or Operator receives
a written complaint related to interference with local broadcast
residential television, the Owner or Operator shall take reasonable
steps to respond to the complaint.
C. Crop Dusting
Applicant will make available a map to all aerial sprayers showing
exact location of all turbines and meteorological towers including the
exact GPS coordinates, township, section number and tower heights.
D. Coordination with Local Fire Department
1. The Applicant, Owner or Operator shall submit to the local fire
department a copy of the Site Plan.
2. The Applicant will communicate with any fire department(s)
providing fire protection for the areas of the proposed WECS and upon
request by the fire department cooperate in the development or revision
of the fire department's emergency response plan.
3. The Applicant shall where reasonably possible link the WECS
project’s fire detection systems with the appropriate fire departments.
4. Nothing in this section shall alleviate the need to comply with
all other applicable fire laws and regulations.
18 August 10, 2010
E. Materials Handling, Storage and Disposal
1. All solid wastes related to the construction, operation and
maintenance of the WECS shall be removed from the site promptly and
disposed of in accordance with all federal, state and local laws.
2. All hazardous materials related to the construction, operation and
maintenance of the WECS shall be handled, stored, transported and
disposed of in accordance with all applicable local, state and federal
laws.
F. Complaint Resolution
The Applicant shall develop a process to resolve any complaints that
may arise from neighboring property owners during the construction and
operation of the WECS. The process shall use an independent mediator and
shall include a time limit for acting on a complaint that is received.
The process shall not preclude the local government from acting on a
complaint. The Applicant shall provide to the nearby residents a
toll-free phone number for complaints during the construction of the
facility if a problem should arise.
Applicant will respond to all complaints from persons directly
affected by the WECS project within 48 hours, will attempt to resolve
all complaints in a prompt and responsible manner, will keep a log of
all complaints and the method of resolution, will make the log available
to County, and will agree to participate in a non-binding mediation for
complaints that are not resolved with the cost of such to be paid
directly by Applicant.
G. Federal, State and Local Requirement Compliance
The Applicant shall comply with all applicable Federal, State and
Local laws and regulations with authority to regulate WECS.
H. County Access
Applicant will allow County officials or their agents, who are in
compliance with the safety and operations requirements associated with
the Project, to investigate any issues arising from the Project at and
by entering the Project area and providing any requested documentation.
Such access shall be granted upon reasonable notice by the County
officials or their agents.
IX. PUBLIC PARTICIPATION
Nothing in the Ordinance is meant to augment or diminish existing
opportunities for public participation.
19 August 10, 2010
X. LIABILITY INSURANCE
The Owner or Operator of the WECS(s) shall maintain a current general
liability policy covering bodily injury and property damage with limits
of at least $5 million per occurrence and $5 million in the aggregate at
all times. The County and all affected Road Districts must be listed as
additional insured.
XI. DECOMMISSIONING PLAN
Prior to receiving siting approval under this Ordinance, the
Applicant, Owner, and/or Operator must provide a Decommissioning Plan to
ensure that the WECS Project is properly decommissioned. The
Decommissioning Plan shall include:
A. An acknowledgement by the Applicant that if WECS is out of service
for a period of 180 days it will be deemed non-operational and removal
of the WECS must commence;
B. An acknowledgement that within 180 days or within a negotiated
time frame dependent upon extenuating circumstances (i.e. seasonal
weather, available labor and equipment) of being determined
non-operational the following must be removed:
1. All wind towers above ground improvements and outside storage.
2. Foundations, pads and electrical lines and reclaim the site to a
depth of four feet (4’) below the surface of the ground.
3. Any hazardous materials or contaminated soils from the WECS
disposed of in accordance with federal and state law.
C. Provisions for the restoration of the soil and vegetation;
D. An estimate of the decommissioning costs certified by a
Professional Engineer to be updated every five years. Such estimate must
explicitly detail the cost before considering the protected salvage
value of out of service WECS.
E. Financial Assurance, posted in cash, escrow account, surety bond
or irrevocable letter of credit, secured by the Owner or Operator, for
the purpose of adequately performing decommissioning, in an amount equal
to 100% of the Structural Engineer's certified estimate of the
decommissioning costs without reducing said amount for salvage value;
F. Identification of and procedures for County access to Financial
Assurances;
G. A provision that the terms of the Decommissioning Plan shall be
binding upon the Owner or Operator and any of their successors, assigns,
or heirs;
20 August 10, 2010
H. A provision that the County shall have access to the site,
pursuant to reasonable notice, to effect or complete decommissioning.
XII. REMEDIES
A. The Applicant's, Owner's, or Operator's failure to materially
comply with any of the above provisions shall constitute a default under
this Ordinance.
B. Prior to implementation of the applicable County procedures for
the resolution of such default(s), the appropriate County body shall
first provide written notice to the Owner and Operator, setting forth
the alleged default(s). Such written notice shall provide the Owner and
Operator a reasonable time period, not to exceed 180 days, for good
faith negotiations to resolve the alleged default(s).
C. If the County determines in its discretion, that the parties
cannot resolve the alleged default(s) within the good faith negotiation
period, then applicable County ordinance provisions addressing the
resolution of such default(s) shall govern.
XIII. PERMIT TRANSFER
The WECS Permit may be transferred by the Applicant only upon the
transferee’s execution and delivery to the County Engineer of a letter
agreeing to be bound by the foregoing conditions.
XIV. TERMS AND LIMITATIONS OF PERMIT
A. Permit Effective Date
The Certificate of Permit shall become effective upon approval by the
County Board.
B. Failure to Commence Construction or Operation
Unless otherwise stated in the conditions of the Certificate of
Permit, initial construction work on the WECS Project shall commence
within twelve (12) months of the effective date of the Certificate of
Permit unless such time period is extended by the County Board. If no
extension of time is granted, the Certificate of Permit shall
immediately terminate upon expiration of the twelve (12) month period.
C. Conditions
The County may impose any conditions to a permit to further the
purposes and intent of this ordinance or minimize non-material impacts
on citizens or other property in the area.
21 August 10, 2010
D. Revocation of Certificate of Permit
Upon finding a material violation of the terms of the Certificate of
Permit, the County Board shall have the authority to revoke the
Certificate of Permit after notice to the Applicant/Permittee and after
affording the Applicant/Permittee an opportunity to be heard.
XV. INDEMNIFICATION, REIMBURSEMENT AND HOLD HARMLESS AGREEMENT
The application shall include an agreement in a form acceptable to
the County by the Applicant, Owner or Operator to the Applicant to
indemnify and hold harmless the County and the County’s officers, Board
members, agents and employees ("indemnitees") from and against any and
all damages, costs, remediation, claims, demands, lawsuits, appeals,
losses, attorneys’ fees and expenses to the extent arising out of or
resulting from a permit authorizing the development, construction,
building and operation of a WECS or WECS Project.
XVI. VARIANCE AND MODIFICATION:
A. Standards for Granting Variances
1. Where an Applicant demonstrates that a provision of this Ordinance
would cause unnecessary hardship, delay or impediments to the
development of a WECS Project if strictly adhered to, and where, in the
opinion of the County Engineer and County Board, because of
topographical or other conditions peculiar to the site, a departure may
be made without destroying the intent of such provisions, the County
Board may authorize a variance, if the variance complies with the
following provisions:
a. The requested variance is required for the development,
construction, operation or decommissioning of the WECS Project, and the
failure to obtain the requested variance would result in a practical
difficulty or unnecessary hardship for the Applicant;
b. The granting of the requested variance will not be materially
detrimental or injurious to any adjacent property;
c. The granting of the requested variance will not violate the
general spirit and intent of this Ordinance.
2. Any variance thus authorized is required to be entered in the
minutes of the County Board meeting, and the reasoning on which the
variance was justified must be described in the minutes as well.
22 August 10, 2010
B. Application for Variance
1. An Applicant for a variance shall file a request for a variance
with the County Clerk within at least 21 days prior to the next
regularly-scheduled County Board meeting. The County Clerk shall place
the Applicant’s request on the agenda for the next County Board meeting.
2. The burden of proof shall rest with the Applicant to clearly
establish that the requested variance satisfies the criteria for
granting such a variance under this Ordinance.
C. Conditions
In granting a variance, the County Engineer and County Board may
impose such conditions and restrictions upon the property benefiting
from the variance as may be necessary to reduce or minimize any
potentially negative impacts on any adjacent properties, and to carry
out the general purpose of this Ordinance.
XVII. INTERPRETATION
The provisions of these regulations shall be held to the minimum
requirements adopted for the promotion and preservation of public
health, safety and general welfare of County of Adams. These regulations
are not intended to repeal, abrogate, annul or in any manner interfere
with existing regulations or laws of the County of Adams nor conflict
with any statutes of the State of Illinois, except that these
regulations shall prevail in cases where these regulations impose a
greater restriction than is provided by existing statutes, laws or
regulations.
XVIII. SEVERABILITY
If any section, paragraph, clause, phrase or part of this Ordinance
is for any reason held invalid by any court or competent jurisdiction,
such decision shall not affect the validity of the remaining provisions
of these regulations, and the application of those provisions to any
persons or circumstances shall not be affected thereby.
XIX. REPEAL
All ordinances and regulations and amendments thereto enacted and/or
adopted by the County Board that are inconsistent with the provisions of
this Ordinance are hereby repealed, as of the effective date of this
Ordinance. The repeal of any prior ordinance or its amendments does not
affect or impair any act done, offense committed or right accruing,
accrued or acquired or liability, penalty, forfeiture or punishment
incurred prior to the time enforced, prosecuted or inflicted.
23 August 10, 2010
XX. CERTIORARI PROCEDURE
In any decision by the County Board under this Ordinance, any person
aggrieved may petition the Circuit Court of Adams County, Illinois, for
a writ of certiorari as provided by law.
XXI. EFFECTIVE DATE
This Ordinance is an ordinance necessary for the health and safety of
the people of Adams County, Illinois, and shall be in full force and
effect from and after its passage.
BE IT FINALLY ORDAINED, that the Board reserves the right to change,
modify or terminate these regulations and procedures at any time, in
whole or in part, for any reason, with or without prior notice upon its
own unilateral act.
________________________________________________
Mike McLaughlin Adams County Board Chairman
________________________________________________
Attest
County Clerk
August 10, 2010
EXHIBIT A
AGREEMENT IN LIEU OF TAXES
The Applicant, its successors and assigns hereby consents and agree
to a permit condition that provides for payments in lieu of taxes under
certain circumstances. Under current Illinois law, 35 ILCS 200/10-600 et
seq. provides a formula for determining the property value assessment of
a wind energy device with a capacity of at least 0.5 mega watts such as
is proposed by the Applicant here. However, that legislation contains a
sundown provision of 2016 and allows for depreciation. A payment will be
made to the County of Adams from the Applicant in an amount not less
than the taxes that are due in the first year of operation based on the
computation of 35 ILCS 200/10-600 et seq. In the event that the tax
payment to the County of Adams for a single turbine when computed under
the existing tax laws would be less than the tax in the first year of
operation, then the Applicant hereby agrees that in consideration of the
impacts on the County of Adams for hosting a wind turbine facility
including possible impacts to roadways, property values, and economy
that the Applicant shall make a payment to Adams County for the
difference between the actual tax for that year and the tax to be paid
under the formula of 35 ILCS 200/10-600 et seq. for the first year of
turbine operation. For example, if the tax in the first year of
operation for a single turbine is determined based on the formula of 35
ILCS 200/10-600 et seq. to be $10,000 and in subsequent years the tax is
determined to be less than that amount then the Applicant shall make an
additional payment to the County of Adams for that difference such that
the total revenue to the County is $10,000 for that tax year. One-half
of the deficiency amount should be paid to the Treasurer of the County
of Adams on behalf of the various taxing bodies on or before the date
that the first installment payment is due pursuant to the tax bill for
the prior calendar year. The remaining one-half of the deficiency amount
shall be paid on or before the date that the second payment is due. Such
payment shall continue for so long as any wind turbine proposed under
the current application is operational. The payment in lieu of taxes
shall be for the total number of turbines allowable under the permit.
Therefore, if the permit allows 13 turbines then the payments shall be
made for each of those 13 turbines for as long as any turbine is in
physical existence at a property located in the County of Adams. The
failure or inability of the Applicant to operate a turbine, to sell its
electrical output, or to generate electricity, shall not be an excuse
from a payment in lieu of taxes. The obligations of the Applicant under
this agreement shall continue even if the Applicant assigns transfers or
sells its interests in the wind turbine project.
The Treasurer of Adams County, on a timely basis, shall distribute
said payments in lieu of taxes to the various taxing bodies in the same
proportion as the actual tax bills. Any other provision herein
notwithstanding, in the event another tax or fee of whatsoever nature is
imposed under any law on a wind turbine in place of or as a substitute
or a replacement for the real property tax or a portion thereof, then
such tax or fees shall for the purpose of this Agreement shall be
treated as if it were a real property tax and taken into account in
determining the amount of payment in lieu of taxes that must be made. If
the revenue to the County of Adams from a substitute or replacement of
the real property tax and taken into account in determining the amount
of payment in lieu of taxes that must be made. If the revenue to the
County of Adams from a substitute or replacement of the real property
tax would exceed the payment under the first year of operation of the
turbine pursuant to 35 ILCS 200/10-600 as that statute existed as of the
date of approval of the permit, then the County of Adams would be
entitled to the higher tax revenue under the substitute or replacement
real property tax and there would be no payment in lieu of taxes to be
made by the Applicant.
|